1. WO2020108361 - PROCÉDÉ DE CONSTRUCTION POUR TUNNEL TRAVERSANT UNE FAILLE RICHE EN EAU DE POUSSÉE ET RICHE EN SABLE À GRAND ANGLE

Numéro de publication WO/2020/108361
Date de publication 04.06.2020
N° de la demande internationale PCT/CN2019/119630
Date du dépôt international 20.11.2019
CIB
E21D 9/00 2006.01
ECONSTRUCTIONS FIXES
21FORAGE DU SOL OU DE LA ROCHE; EXPLOITATION MINIÈRE
DPUITS; TUNNELS; GALERIES; VASTES CHAMBRES SOUTERRAINES
9Tunnels ou galeries, avec ou sans revêtements; Procédés ou appareils pour leur exécution; Tracé des tunnels ou des galeries
CPC
E21D 11/10
EFIXED CONSTRUCTIONS
21EARTH DRILLING; MINING
DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
11Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
04Lining with building materials
10with concrete cast in situ; Shuttering ; also lost shutterings, e.g. made of blocks, of metal plates; or other equipment adapted therefor
E21D 11/14
EFIXED CONSTRUCTIONS
21EARTH DRILLING; MINING
DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
11Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
14Lining predominantly with metal
E21D 11/18
EFIXED CONSTRUCTIONS
21EARTH DRILLING; MINING
DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
11Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
14Lining predominantly with metal
18Arch members ; ; Network made of arch members
E21D 9/00
EFIXED CONSTRUCTIONS
21EARTH DRILLING; MINING
DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
9Tunnels or galleries, with or without linings; Methods or apparatus for making thereof
E21F 16/02
EFIXED CONSTRUCTIONS
21EARTH DRILLING; MINING
FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
16Drainage
02of tunnels
Déposants
  • 中铁二十局集团有限公司 CHINA RAILWAY 20 BUREAU GROUP CORPORATION [CN]/[CN]
Inventeurs
  • 吴应明 WU, Yingming
  • 张旭辉 ZHANG, Xuhui
  • 高雷州 GAO, Leizhou
  • 张乃乐 ZHANG, Naile
  • 周中财 ZHOU, Zhongcai
  • 肖清华 XIAO, Qinghua
  • 仲维玲 ZHONG, Weiling
  • 郭朋超 GUO, Pengchao
  • 王洪坤 WANG, Hongkun
  • 赵志辉 ZHAO, Zhihui
  • 李校珂 LI, Xiaoke
  • 杨文 YANG, Wen
  • 杨荣辉 YANG, Ronghui
  • 李越兴 LI, Yuexing
  • 陈创 CHEN, Chuang
  • 洪平 HONG, Ping
Mandataires
  • 西安创知专利事务所 XI'AN CHUANG ZHI PATENT AGENCY
Données relatives à la priorité
201811414022.726.11.2018CN
Langue de publication chinois (ZH)
Langue de dépôt chinois (ZH)
États désignés
Titre
(EN) CONSTRUCTION METHOD FOR TUNNEL PASSING THROUGH HIGH-ANGLE THRUST WATER-RICH AND SAND-RICH FAULT
(FR) PROCÉDÉ DE CONSTRUCTION POUR TUNNEL TRAVERSANT UNE FAILLE RICHE EN EAU DE POUSSÉE ET RICHE EN SABLE À GRAND ANGLE
(ZH) 穿越高角度逆冲富水富砂断层隧道施工方法
Abrégé
(EN)
Disclosed is a construction method for a tunnel passing through a high-angle thrust water-rich and sand-rich fault, comprising the following steps: 1, performing the preliminary excavation and the supporting construction of a rear-side tunnel section (3); 2, performing the synchronous excavation and the supporting construction of the rear-side tunnel section (3) and a drainage cave body of a drainage cave (2); 3, performing the synchronous excavation and the supporting construction of the rear-side tunnel section (3), the drainage cave body of the drainage cave (2), and a rear-side detouring heading pit (1) section; 4, performing the excavation and the supporting construction of a front drainage cave (2) body, a front heading pit section, and a central tunnel section (5); and 5, performing the excavation and the supporting construction of a front-side tunnel section (4). The water on the upper wall of the fault is drained by means of a high-level drainage cave between a tunnel main cave and a detouring heading pit, and the auxiliary drainage is performed by means of the detouring heading pit and the fault condition in front of a tunnel face of the main cave is explored in advance, thereby ensuring the construction safety of each tunnel face. The method employs a three-step method for the excavation of the tunnel main cave, employs double preliminary supporting structures for the full-section supporting of a tunnel cave after excavation, can ensure the safety of the tunnel structure later, and shortens the construction cycle.
(FR)
L'invention concerne un procédé de construction pour un tunnel traversant une faille riche en eau de poussée et riche en sable à grand angle, comprenant les étapes suivantes : 1, à effectuer l'excavation préliminaire et de la construction de support d'une section de tunnel côté arrière (3) ; 2, à effectuer l'excavation synchrone et de la construction de support de la section de tunnel côté arrière (3) et d'un corps de caverne de drainage d'une caverne de drainage (2) ; 3, à effectuer l'excavation synchrone et de la construction de support de la section de tunnel côté arrière (3), du corps de caverne de drainage de la caverne de drainage (2), et d'une section de fosse d'avancement de détournement côté arrière (1) ; 4, à effectuer l'excavation et de la construction de support d'une caverne de drainage avant (2), d'une section de fosse d'avancement avant et d'une section de tunnel centrale (5) ; et 5, à effectuer l'excavation et de la construction de support d'une section de tunnel côté avant (4). L'eau sur la paroi supérieure de la faille est drainée au moyen d'une caverne de drainage de haut niveau entre une caverne principale de tunnel et une fosse d'avancement de détournement, et le drainage auxiliaire est effectué au moyen de la fosse d'avancement de détournement et l'état de la faille devant une face de tunnel de la caverne principale est explorée à l'avance, ce qui permet d'assurer la sécurité de construction de chaque face de tunnel. Le procédé emploie un procédé en trois étapes pour l'excavation de la caverne principale de tunnel, utilise des structures de support préliminaires doubles pour le support en section entière d'une caverne de tunnel après excavation, peut assurer la sécurité de la structure de tunnel ultérieurement, et raccourcit le cycle de construction.
(ZH)
公开了一种穿越高角度逆冲富水富砂断层隧道施工方法,包括步骤:一、后侧隧道段(3)初步开挖及支护施工;二、后侧隧道段(3)与泄水洞(2)排水洞体同步开挖及支护施工;三、后侧隧道段(3)、泄水洞(2)排水洞体与后侧迂回导坑(1)段同步开挖及支护施工;四、前部泄水洞(2)体、前部导坑段与中部隧道段(5)开挖及支护施工:五、前侧隧道段(4)开挖及支护施工。通过在隧道正洞与迂回导坑之间的高位泄水洞排出断层上盘赋水,同时通过迂回导坑进行辅助排水并提前探明正洞掌子面前方断层情况,能保证各掌子面施工安全,采用三台阶法对隧道正洞进行开挖,并且开挖后采用双层初期支护结构对隧道洞进行全断面支护,能确保后期隧道结构安全,缩短施工工期。