(EN) [Problem] The present invention appraises progress per work day at a construction site. [Solution] A construction site progress appraisal system 100 acquires the image of a construction site 50 of the day of work aerially imaged by an imaging means 42 mounted in a drone 40 (step S1). A server 10 processes the acquired construction site image into three-dimensional data 16B. Meanwhile, a difference between the three-dimensional data 16B and a design drawing 16C of the construction site 50 is extracted (step S3), and progress of the day of work is appraised in accordance with the extracted difference. Work instructions for tomorrow and onward are given to site workers 60 in accordance with the appraisal (step S4).
(FR) La présente invention a pour objet d'évaluer la progression par jour de travail au niveau d'un chantier. À cet effet, l’invention porte sur un système d'évaluation de progression de chantier qui acquiert l'image d'un chantier 50 du jour de travail imagé de manière aérienne par un moyen d'imagerie 42 monté dans un drone 40 (étape S1). Un serveur 10 traite l'image de chantier acquise en données tridimensionnelles 16B. Pendant ce temps, une différence entre les données tridimensionnelles 16B et un dessin de conception 16C du chantier 50 est extraite (étape S3), et la progression du jour de travail est estimée conformément à la différence extraite. Des instructions de travail relatives aux jours suivants sont données à des travailleurs sur chantier 60 selon l'évaluation (étape S4).
(JA) 【課題】本発明は、工事現場における作業日毎の出来高評価を行う。 【解決手段】工事現場出来高評価システム100は、ドローン40に搭載された撮影手段42によって空撮された作業当日の工事現場50の画像を取得する(ステップS1)。サーバ10は、取得した工事現場の画像を、3次元データ16Bに処理する。そして、前記3次元データ16Bと、工事現場50の設計図面16Cとの差分を抽出し(ステップS3)、抽出した差分に応じて、作業当日の出来高を評価する。評価に応じて、現場作業員60に、明日以降の作業指示を行う(ステップS4)。