1. WO2020062715 - METHOD AND APPARATUS FOR ALLOCATING LOAD SHEDDING AMOUNT

Publication Number WO/2020/062715
Publication Date 02.04.2020
International Application No. PCT/CN2019/071558
International Filing Date 14.01.2019
IPC
G06Q 10/00 2012.01
GPHYSICS
06COMPUTING; CALCULATING OR COUNTING
QDATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES, NOT OTHERWISE PROVIDED FOR
10Administration; Management
H02J 3/14 2006.01
HELECTRICITY
02GENERATION, CONVERSION, OR DISTRIBUTION OF ELECTRIC POWER
JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
3Circuit arrangements for ac mains or ac distribution networks
12for adjusting voltage in ac networks by changing a characteristic of the network load
14by switching loads on to, or off from, network, e.g. progressively balanced loading
H02J 13/00 2006.01
HELECTRICITY
02GENERATION, CONVERSION, OR DISTRIBUTION OF ELECTRIC POWER
JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
13Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
CPC
G06Q 10/06312
GPHYSICS
06COMPUTING; CALCULATING; COUNTING
QDATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES, NOT OTHERWISE PROVIDED FOR
10Administration; Management
06Resources, workflows, human or project management, e.g. organising, planning, scheduling or allocating time, human or machine resources; Enterprise planning; Organisational models
063Operations research or analysis
0631Resource planning, allocation or scheduling for a business operation
06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
G06Q 50/06
GPHYSICS
06COMPUTING; CALCULATING; COUNTING
QDATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES, NOT OTHERWISE PROVIDED FOR
50Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
06Electricity, gas or water supply
Applicants
  • 南京南瑞继保电气有限公司 NR ELECTRIC CO., LTD [CN]/[CN]
  • 南京南瑞继保工程技术有限公司 NR ENGINEERING CO., LTD [CN]/[CN]
Inventors
  • 白杨 BAI, Yang
  • 任祖怡 REN, Zuyi
  • 夏尚学 XIA, Shangxue
  • 王鹏翔 WANG, Pengxiang
  • 王良 WANG, Liang
  • 徐柯 XU, Ke
  • 李龙龙 LI, Longlong
  • 祝万 ZHU, Wan
  • 高楠 GAO, Nan
  • 王君超 WANG, Junchao
Agents
  • 南京经纬专利商标代理有限公司 NANJING JINGWEI PATENT & TRADEMARK AGENCY CO., LTD
Priority Data
201811153728.230.09.2018CN
Publication Language Chinese (ZH)
Filing Language Chinese (ZH)
Designated States
Title
(EN) METHOD AND APPARATUS FOR ALLOCATING LOAD SHEDDING AMOUNT
(FR) PROCÉDÉ ET APPAREIL D'ATTRIBUTION DE QUANTITÉ DE DÉLESTAGE DE CHARGE
(ZH) 一种切负荷量分配方法及装置
Abstract
(EN)
Disclosed is a method for allocating a load shedding amount, comprising the following steps: (1) proportionally allocating, without rounding, a total required shedding amount according to sheddable load amounts of load shedding sub-stations to obtain initial allocation amounts of the load shedding sub-stations, counting the sum of the initial allocation amounts of the load shedding sub-stations, i.e., the total initial allocation amount, and calculating a difference between the total required shedding amount and the total initial allocation amount, i.e., a remaining required shedding amount; (2) calculating allocation remainders of the load shedding sub-stations after the allocation of an initial allocation module; (3) sorting the allocation remainders according to a descending order; and (4) for the remaining required shedding amount, additionally allocating load shedding amounts to the load shedding sub-stations according to the order of descending allocation remainders until the total required shedding amount is equal to a total allocation amount. Also disclosed is a corresponding apparatus for allocating a load shedding amount. The solution of the present invention improves the accuracy of the allocation of a load shedding amount, and can effectively avoid overshedding or undershedding caused by rounding.
(FR)
L'invention concerne un procédé d'attribution de quantité de délestage de charge, comprenant les étapes suivantes : (1) attribution proportionnelle, sans arrondi, d'une quantité de délestage requise totale en fonction de quantités de charge délestables de postes électriques de délestage de charge pour obtenir des quantités d'attribution initiales des postes électriques de délestage de charge, comptage de la somme des quantités d'attribution initiales des postes électriques de délestage de charge, c'est-à-dire de la quantité d'attribution initiale totale, et calcul d'une différence entre la quantité de délestage requise totale et la quantité d'attribution initiale totale, c'est-à-dire d'une quantité de délestage requise restante ; (2) calcul de restes d'attribution des postes électriques de partage de charge après attribution d'un module d'attribution initial ; (3) tri des restes d'attribution dans un ordre décroissant ; et (4) pour la quantité de délestage requise restante, attribution supplémentaire de quantités de délestage de charge aux postes électriques de délestage de charge dans l'ordre décroissant des restes d'attribution jusqu'à ce que la quantité de délestage requise totale soit égale à une quantité d'attribution totale. L'invention concerne également un appareil d'attribution de quantité de délestage de charge correspondant. La solution de la présente invention améliore la précision de l'attribution d'une quantité de délestage de charge, et peut efficacement éviter un sur-délestage ou un sous-délestage provoqués par un arrondi.
(ZH)
本发明公开一种切负荷量分配方法,包括如下步骤:(1)按照各切负荷子站可切负荷量成比例分配总需切量,分配时不进行四舍五入,得到各切负荷子站初始分配量,并统计各切负荷子站初始分配量的总和即初始分配总量,计算总需切量与初始分配总量的差值即剩余需切量;(2)计算初始分配模块分配后各切负荷子站的分配余数;(3)对分配余数按照从大到小的顺序排列;(4)剩余需切量按照分配余数从大到小的顺序在各切负荷子站追加分配切负荷量,直到总需切量与总分配量相等为止。本发明还公开了相应的切负荷量分配装置。本发明的方案提高了切负荷量分配精度,可有效避免四舍五入造成的过切或欠切。