1. AU2003268690 - Method of producing natural stone panel

Office
Australia
Application Number 2003268690
Application Date 29.09.2003
Publication Number 2003268690
Publication Date 08.01.2004
Publication Kind A
IPC
B28B 23/00
BPERFORMING OPERATIONS; TRANSPORTING
28WORKING CEMENT, CLAY, OR STONE
BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS, SLAG OR MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
23Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material
B28B 1/16
BPERFORMING OPERATIONS; TRANSPORTING
28WORKING CEMENT, CLAY, OR STONE
BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS, SLAG OR MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
1Producing shaped articles from the material
14by simple casting, the material being neither forcibly fed nor positively compacted
16for producing layered articles
B28B 7/02
BPERFORMING OPERATIONS; TRANSPORTING
28WORKING CEMENT, CLAY, OR STONE
BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS, SLAG OR MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
7Moulds; Cores; Mandrels
02Moulds with adjustable parts
B28B 23/02
BPERFORMING OPERATIONS; TRANSPORTING
28WORKING CEMENT, CLAY, OR STONE
BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS, SLAG OR MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
23Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material
02wherein the elements are reinforcing members
E02B 3/14
EFIXED CONSTRUCTIONS
02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL-SHIFTING
BHYDRAULIC ENGINEERING
3Engineering work in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering work in general
04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
12Revetment of banks, dams, watercourses, or the like
14Preformed blocks; Arrangements thereof
E02D 29/02
EFIXED CONSTRUCTIONS
02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL-SHIFTING
DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
29Underground or underwater structures; Retaining walls
02Retaining or protecting walls
CPC
E02B 3/14
EFIXED CONSTRUCTIONS
02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
BHYDRAULIC ENGINEERING
3Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites
04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
12Revetment of banks, dams, watercourses, or the like, ; e.g. the sea-floor
14Preformed blocks ; or slabs for forming essentially continuous surfaces; Arrangements thereof
B28B 23/0075
BPERFORMING OPERATIONS; TRANSPORTING
28WORKING CEMENT, CLAY, OR STONE
BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
23Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; ; Production of reinforced objects
0075for decorative purposes
E02D 29/0291
EFIXED CONSTRUCTIONS
02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS
29Independent; underground or underwater structures
02Retaining or protecting walls
0258characterised by constructional features
0291made up of filled, bag-like elements
Applicants SOLVE CORPORATION CO., LTD.
Inventors Hayashi, Hiroshi
Priority Data 2002285457 30.09.2002 JP
Title
(EN) Method of producing natural stone panel
Abstract
(EN) A method of producing a natural stone panel where plural natural stones are solidly fixed, arranged along a curved face. The method includes a step of arranging plural large-diameter natural stones on a bottom plate whose upper face is bent in a concave or convex form, a step of bedding granular bodies such as sand on the upper face of the bottom plate from individual gaps between the large-diameter natural stones to a thickness equal to or less than half the height of the natural stones, a step of closing the individual gaps by arranging small-diameter natural stones in the gaps, and a step of installing an upper frame on the upper part of a lower frame and solidifying a solidification material such as ready-mixed concrete poured from an opening above the upper frame.